Aiming at the key parts production line of diesel engine planned by H company, two production line schemes were proposed, the simulation models were established based on Plant Simulation platform, and the monthly output and equipment utilization rate were analyzed. The results show that the scheme one is far better than the scheme two in terms of capacity and equipment utilization regardless of whether there is cache; after the cache capacity configuration is completed, the capacity and equipment utilization of the 〖JP3〗two schemes are greatly improved; after comprehensive analysis and evaluation of the two schemes, the scheme one has better performance.
参考文献
相似文献
引证文献
引用本文
文传奇,杜兵,张鹏.柴油机关键件生产线的方案设计研究[J].机床与液压,2022,50(1):121-124. WEN Chuanqi, DU Bing, ZHANG Peng. Research on the Scheme Design of Key Parts Production Line for Diesel Engine[J]. Machine Tool & Hydraulics,2022,50(1):121-124